AGNEW GAS PIPELINE FACILITIES

Scope of Works

Alltype Engineering was contracted to provide full turnkey facilities construction works for APA Group as a part of the overall Agnew Gas Pipeline Construction Project.

This project involved works across two remote construction sites; the Agnew Delivery Station and Kyarra Offtake Station, with SIMOP’s comprising the following disciplines:

  • Offsite workshop fabrication of high-pressure facility piping to ASME B31.3
  • Offsite workshop fabrication of high-pressure gas pipeline piping and components to AS 2885.2 
  • Site establishment 
  • Bulk Earthworks including site grading and pad build up
  • Precast Concrete Installation
  • Structural, Mechanical and Piping (SMP) installation of skids, structural platform and racks, interconnecting piping and inlet pipeline from the GGP
  • NDT, hydrotesting, surface treatment and tie-in works
  • Electrical and Instrumentation (E&I) including offsite workshop fit-out of the facility Control Room
  • Hazardous Area Installation and EEHA Inspections
  • Pre-Commissioning and Commissioning Support prior to Facilities handover to APA

Being awarded this project was a great achievement for Alltype Engineering and was followed with an aggressive delivery schedule that was completed within a very short 8 weeks site schedule with zero incidents.

Project Description

Client:

APA Group

Location:

Leinster, Western Australia

Year:

2019

Scope of works:

Multidiscipline Procurement, Fabrication, Construction and Installation Works – Civil, Concrete, Structural, Mechanical, Piping, Electrical, Instrumentation